Timetable of events
1949 Born
1960 - 64 Build & fly model gliders
1966 Get British pilots licence
1968 Study Aeronautical Engineering & Physics at Salford University
1969 Join RAF as pilot
1971 Leave RAF
1981 Emmigrate to USA
1984 Get US Pilots licence
1988 Buy Cherokee 160
1996 Sell Cherokee 160
Jan 99 Decide to build a canard homebuild
research types, models, companys, suppliers
decide on cozy
Feb 99 2/5/99 Order Cozy plans
2/23/99 receive Cozy plans
2/24/99 Order materials for 1st 4 chapters
2/24/99 Order tools, epoxy pump etc.
Build workbench
prepare shop
visit AeroCanard Ltd.
Order owners manual
meet cozy builder in Ft. Lauderdale
Mar 99
3/6/99 start building
3/18/99 visited by EAA technical consultants
3/29/99 order smart level plus addl supplies
complete Chapters 4 & 5
Apr 99 4/11/99 Sun & Fun. Cozy dinner.
Met Nat & Shirly, Steve Wright, Jack Wilhelmson, Dave Higgins and many more.
Order main strut from Featherlite
Order antenna materials & audio panel from RST (530-272-2203).
complete Chapters 6 & 7
May 99 Complete Chapters 8 & 9
5/28/99 Flip the plane onto its wheels.
Build RST Audio Panel
June 99 Complete Chapter 10, Canard
Work on Chaps 11, 12, 13, 24 & 25
July 99 Waiting for parts in numerous chapters
Work on Chaps 11, 12, 13, 24 & 25
Missed OSH. Maybe next year, in N386JS?
August 99 Complete main spar. Work on Chap 17.
Sept 99 Complete elevators. Start on wings.
Oct 99 Complete winglets. Work on wings.
Nov 99 Work on wings
Dec 99 Complete wings, attach winglets.
Complete ailerons & rudders
Start strakes and turtleback
Jan 00 Complete turtleback and strakes
Feb 00 Primary finishing - top
Mar 00 Primary finishing - bottom
Apr 00 Sun & Fun 2000
Visit from Wayne Hicks & George Shell
Chap 16 - controls
May 00 Chap 18 - canopy
Jun 00 Chap 15 - Firewall
Finish the canopy deck and turtleback
Jul 00 Complete firewall
Aug 00 Install seats & armrests
begin upholstery
build sump tank behind rear seats
plan instrument panel
Sep 00 No progress to speak of
Did almost nothing to the plane work till June 01.
Oct 00 Take delivery of 13B engine
RWS EFI computer & redrive received
Minor finishing work
Nov 00 Canopy latch system
Dec 00 Install nose wheel and lift
Jan 01 Make nose gear doors
Feb 01 some finishing work
engine mounting
Mar 01 more finishing work
Apr 01 more finishing work
Jun 01 more finishing work
Jul 01 complete bottom gloss paint
mount bare engine & redrive
make lower cowling
more finishing work
Aug 01 make upper cowling
more finishing work
gloss paint control surfaces / canard
fit cowlings
modify cowlings